Welcome to the Park Cities YMCA Construction Update page. All updates concerning the construction of the new Moody Family YMCA in the Park Cities will be posted here. If you would like to opt into the Update Emails please send your contact information to Roger Moon at rmoon@ymcadallas.org

Currently the Park Cities YMCA is located in an interim location in Preston Center next to Hopdoddys.  We will remain in the interim space throughout the construction period.

After 63 years, the YMCA is building a new Y in the Park Cities to better serve the community. The facility will be located on the site of the current YMCA at 6000 Preston Road.  The facility will include a 281 space underground parking facility, gymnasium, indoor pool along with a family and therapy pool, wellness center, multi- purpose space for youth programs, a preschool center and outdoor recreation fields.

Slated to open in the fall of 2016, the new Moody Family YMCA will be a vibrant Y that can serve the needs of kids, teens , families and seniors in the Park Cities for generations to come.

UPDATE:

Lot of progress has been made on the Moody Family YMCA in the Park Cities.  Specific Tasks completed include:

 

Pool Gunnite Installation

Backfill Basement Walls

Building Dried-in

Transformer Delivered/ Installed

Exterior Building Waterproofing

Structural Steel Detailing

 

Click here for the latest time-lapse video of the building progress




General Construction Timeline

Stone Veneer: March 15-June 20

Permanent Power Established: June 6

Waterproof Garage Lip: May 15- June 30

Backfill Lid: June 10- July 8

Landscape & Irrigation: June 27-August 15

Elevator Install: June 7-June 24

Millwork Install: June 1-July 1

Gym Equipment and Flooring: June 6-July 11

Fill Pool: July 11-August 3



September 19, 2016: YMCA Occupancy

 


How long is the construction expected last?

Present to September 2016

 

What are the Construction Zone hours?                                                

7:00am to 6:00 pm Monday – Saturday for onsite work.  No work on Sunday.

Truck arrival and departures between the hours to 7:00 am and 6:00 pm

 

How will the construction impact traffic?

Trucks will be limited to Preston Road and Normandy, with the exception being along Connerly when the demolition, site utilities, and concrete pavement repair is taking place.  These activities will be done throughout various phases of the project and thus will impact traffic accordingly.  When possible we will post notices in advance of the work taking place.   

 




Will there be lane closures?

During underground utility work there will be various partial lane closures along Connerly and Normandy.  Flagman will be used as needed to direct traffic around the work. Potential single lane closures on Preston Road during demolition of the existing paving and potentially for final garage concrete work



How will the new YMCA be Landscaped?


Frequently Asked Questions

What is the routing for trucking and deliveries?

See attached Site Logistics plan for details.  Trucks will enter the site initially off of Preston and exit to the site along the south side off Normandy.  They will then turn right onto Preston and head north.

 

What are the parking arrangement for the workers?

Workers will park off site outside of University Park and be bussed to construction site.

Onsite Forman and supervisors will have a few trucks parked onsite.

 

How can I get updates on the construction project?

Throughout the project, updates will be available on the YMCA’s website at http://www.pcymcaconstruction.org  additionally you can find updates on Park Cities YMCA Facebook page. 

 

To join the YMCA Project update email list please send your name and email to rmoon@ymcadallas.org

 

Who is the construction project contact?

Pritchard Associates – Project Manager

Main Office –214-849-0011

Kyle Nix – Cell: 817-739-6925 kyle@pritchardassociates.com

 

Adolfson & Peterson Construction - Contractor

Main Office – 972-387-1700

Zack Rogers – Sr. Project Manager –

Cell: 214-476-3450 zrogers@a-p.com

Randy Allen – Sr. Superintendent –

Cell: 214-864-7978 rallen@a-p.com